2.7 Test C-Connector Signals
Check List · Step 7 of 12 · Switch the C connector EN / STP / DIR signals one at a time
🎯 Objective
The XYYZA test file uses the final C connector as three ordinary diagnostic outputs. Follow the commands from top to bottom and confirm each indicator switches independently.
Keep the external driver disconnected. These commands control the pins assigned by the active YAML. Do not reuse them on another board without checking that board’s configuration.

Use the last physical driver group in numbered area ⑩: C EN = I2SO.23, C STP = I2SO.21, C DIR = I2SO.20. Click to enlarge.
🧪 How to Test
Open WebUI Console. Send one row, observe the indicated C-connector LED or measure the signal relative to C GND, then continue to the next row.
M7→C EN · I2SO.23ON
M9→C ENOFF
M8→C STP · I2SO.21ON
M9→C STPOFF
M64 P0→C DIR · I2SO.20ON
M65 P0→C DIROFF
✅ Pass: C EN follows
M7/M9, C STP follows M8/M9, C DIR follows M64 P0/M65 P0, and only the selected signal changes.pibot_cnc_laser_series/v47b/test_aux_outputs/start.txt · Last modified: by 127.0.0.1